Updating task status updates resource status
Explanation
Automatically updates resource status, such as actual and remaining work and cost, whenever you update task status, such as percent complete, actual duration, or remaining duration.
If you enable this setting, task status updates are automatically applied to resources.
If you disable or do not configure this setting, the user's default setting is used.
Registry
HKEY_CURRENT_USER\software\policies\microsoft\office\16.0\ms project\options\calculation- Value name
auto track resources
| State | Value written |
|---|---|
| Enabled | REG_DWORD = 1 |
| Disabled | REG_DWORD = 0 |
PowerShell
PowerShell commands that write to the registry what the policy would write. Values in angle brackets (<…>) must be replaced.
Writing directly to the registry bypasses Group Policy: if a GPO manages this value, it will be rewritten at the next gpupdate; otherwise the value stays in place (the "tattooing" effect). Prefer a GPO or, locally, LGPO.exe. Run PowerShell as administrator for HKLM. Some policies need a restart or gpupdate /force.
Enable
# Enable: proj16/L_PjUpdatingTask
$k = 'HKCU:\software\policies\microsoft\office\16.0\ms project\options\calculation'
if (-not (Test-Path -Path $k)) { New-Item -Path $k -Force | Out-Null }
Set-ItemProperty -Path $k -Name 'auto track resources' -Value 1 -Type DWordDisable
# Disable: proj16/L_PjUpdatingTask
$k = 'HKCU:\software\policies\microsoft\office\16.0\ms project\options\calculation'
if (-not (Test-Path -Path $k)) { New-Item -Path $k -Force | Out-Null }
Set-ItemProperty -Path $k -Name 'auto track resources' -Value 0 -Type DWordRevert to "Not configured"
# Revert to "Not configured": proj16/L_PjUpdatingTask
$k = 'HKCU:\software\policies\microsoft\office\16.0\ms project\options\calculation'
Remove-ItemProperty -Path $k -Name 'auto track resources' -ErrorAction SilentlyContinueApplication
Microsoft 365 Apps / Office (Microsoft) — November 2026 templates