Open in the explorer

Inserted projects are calculated like summary tasks

Type
User
GPO path
User Configuration › Policies › Administrative Templates › Microsoft Project 2016 › Project Options › Calculation › Calculation options for 'Project1'
Supported on
At least Windows Server 2008 R2 or Windows 7
ADMX file
proj16.admx
Internal name
proj16/L_PjInsertedProjects

Explanation

Specifies that a single critical path is calculated throughout the master project, by treating inserted projects as summary tasks in the master project.

If you enable this setting, the critical path is calculated by treating inserted projects as summary tasks.

If you disable or do not configure this setting, the user's default setting is used.

Registry

HKEY_CURRENT_USER\software\policies\microsoft\office\16.0\ms project\options\calculation
Value name
inserted projects are calculated like summary tasks
StateValue written
EnabledREG_DWORD = 1
DisabledREG_DWORD = 0

PowerShell

PowerShell commands that write to the registry what the policy would write. Values in angle brackets (<…>) must be replaced.

Writing directly to the registry bypasses Group Policy: if a GPO manages this value, it will be rewritten at the next gpupdate; otherwise the value stays in place (the "tattooing" effect). Prefer a GPO or, locally, LGPO.exe. Run PowerShell as administrator for HKLM. Some policies need a restart or gpupdate /force.

Enable

# Enable: proj16/L_PjInsertedProjects
$k = 'HKCU:\software\policies\microsoft\office\16.0\ms project\options\calculation'
if (-not (Test-Path -Path $k)) { New-Item -Path $k -Force | Out-Null }
Set-ItemProperty -Path $k -Name 'inserted projects are calculated like summary tasks' -Value 1 -Type DWord

Disable

# Disable: proj16/L_PjInsertedProjects
$k = 'HKCU:\software\policies\microsoft\office\16.0\ms project\options\calculation'
if (-not (Test-Path -Path $k)) { New-Item -Path $k -Force | Out-Null }
Set-ItemProperty -Path $k -Name 'inserted projects are calculated like summary tasks' -Value 0 -Type DWord

Revert to "Not configured"

# Revert to "Not configured": proj16/L_PjInsertedProjects
$k = 'HKCU:\software\policies\microsoft\office\16.0\ms project\options\calculation'
Remove-ItemProperty -Path $k -Name 'inserted projects are calculated like summary tasks' -ErrorAction SilentlyContinue